Content provided by Staticworx. All podcast content including episodes, graphics, and podcast descriptions are uploaded and provided directly by Staticworx or their podcast platform partner. If you believe someone is using your copyrighted work without your permission, you can follow the process outlined here https://player.fm/legal.
Player FM - Podcast App
Go offline with the Player FM app!

Case Study – Replacing a Failing Floor Without Losing Production Time

10:49
 
Share
 

Manage episode 249704295 series 2495711
Content provided by Staticworx. All podcast content including episodes, graphics, and podcast descriptions are uploaded and provided directly by Staticworx or their podcast platform partner. If you believe someone is using your copyrighted work without your permission, you can follow the process outlined here https://player.fm/legal.

StaticWorx was asked to evaluate a failing floor in an electronics manufacturing facility. After a fire the client had purchased a new ESD vinyl tile floor. Three months into the installation the floor was already lifting. In addition to unmitigated vapor, the building had been built using tilt-up construction. Silicone bond-breakers - sprayed on the concrete to keep the wall slabs from adhering to the subfloor - contaminated the concrete, preventing the tile from adhering properly. As the building was operational and the client wanted to avoid shutdown, Dave recommended interlocking ESD vinyl tile. StaticWorx installed a 10’ x 10’ test patch. Two months later, the interlocking floor was intact. StaticWorx covered the entire floor in the operational facility with interlocking vinyl tile - without the client’s losing a day of production.

The post Static Bursts (Ep #17): Case Study – Replacing a Failing Floor Without Losing Production Time appeared first on StaticWorx Learning Center.

  continue reading

21 episodes

Artwork
iconShare
 
Manage episode 249704295 series 2495711
Content provided by Staticworx. All podcast content including episodes, graphics, and podcast descriptions are uploaded and provided directly by Staticworx or their podcast platform partner. If you believe someone is using your copyrighted work without your permission, you can follow the process outlined here https://player.fm/legal.

StaticWorx was asked to evaluate a failing floor in an electronics manufacturing facility. After a fire the client had purchased a new ESD vinyl tile floor. Three months into the installation the floor was already lifting. In addition to unmitigated vapor, the building had been built using tilt-up construction. Silicone bond-breakers - sprayed on the concrete to keep the wall slabs from adhering to the subfloor - contaminated the concrete, preventing the tile from adhering properly. As the building was operational and the client wanted to avoid shutdown, Dave recommended interlocking ESD vinyl tile. StaticWorx installed a 10’ x 10’ test patch. Two months later, the interlocking floor was intact. StaticWorx covered the entire floor in the operational facility with interlocking vinyl tile - without the client’s losing a day of production.

The post Static Bursts (Ep #17): Case Study – Replacing a Failing Floor Without Losing Production Time appeared first on StaticWorx Learning Center.

  continue reading

21 episodes

All episodes

×
 
Loading …

Welcome to Player FM!

Player FM is scanning the web for high-quality podcasts for you to enjoy right now. It's the best podcast app and works on Android, iPhone, and the web. Signup to sync subscriptions across devices.

 

Quick Reference Guide